Central Hookup - Farm

Overhead Service - Residential

Underground Metering Point

Underground Secondary Service from Existing Overhead Primary Pole - Residential

Underground Secondary Service from Existing Underground Primary Vault - Residential

Temporary Overhead Service using Entrance Cable for Construction

Temporary Overhead Service using Conduit for Construction

Temporary Underground Service for Construction

Temporary Overhead Service for Trailer using Entrance Cable

Temporary Overhead Service for Trailer using Conduit

Primary Underground/Secondary Underground Service - Residential

Housing Development - Primary Underground Vault Specifications

 

 

Standard new service fee up to 200 amp meter base is $250.

Note: Customer is responsible for all trenching and backfilling, 3 inch sch.40 PVC required for secondary cable.

 

Service
Charge
All new services
will be charged $250.00
Overhead Primary
Permanent Residence Mobile Home Seasonal Home
$4.30/ft. over 900 ft.
along public road
$4.30/ft. over 300 ft.
off public road

Overhead Secondary

No charge - 200 ft. maximum
Underground Secondary

150 ft. (trench length)
4/0 TX - no charge
$2.00/ft. over first 100 ft.
for 350 MCM TX (maximum
250 ft. trench length)

Underground Primary
Individual

Developer


$1.00/ft. up to 300 ft. off road
$5.30/ft. plus $2500
for each transformer Holmes-Wayne
furnishes 2 inch pipe.
Actual cost, reimbursed per
lot hook-up for maximum
of five years.

Right-of-Way Clearing - 1st time

Customer clears ROW
on his own property.
Holmes-Wayne clears
ROW in all other areas,
public, or private.


Temporary Service

No Charge

Oil Wells & Freezer Barns
Primary Overhead
$4.30/ft. for entire line length